Measure P was approved on June 7th, 2016 to help modernize and improve the District's middle school and six elementary schools. These are the first projects funded by Measure P:- Blanchard Window Replacement project (completed 2017)
- Isbell Science Classrooms project (occupied December 2018)
- Barbara Webster Parking Lot project (opened August 2019)
- Isbell Literacy Center project (occupied August 2019)
- Grace Thille Lunch Shelter project (completed 2019)
- Classroom Air Conditioning at Barbara Webster, Blanchard, Glen City and Grace Thille (completed 2019)
- Bedell Electrical Upgrades project (completed 2020)
- Glen City Sidewalk Replacement project (completed December 2020)
- Barbara Webster Painting project (completed March 2021)
The following projects are currently underway or in design phase:
- Blanchard Painting project (bids close April 6, 2021)
- Barbara Webster Lunch Shelter project (architect retained November 2020)
- Classroom Air Conditioning at Bedell (in progress during 2021)
- Isbell Interim Housing project (architect retained November 2020)
- McKevett Electrical Upgrade project (design underway)
Bond Oversight Advisory Committee
The committee's three current members were appointed November 9, 2016, and the District is actively seeking new committee members. Please e-mail dhenning@santapaulaunified.org to obtain an application for committee membership.The next meeting is scheduled for 5:00PM on May 18, 2021; the meeting will be held via Zoom. Agenda for the next meeting: Not yet postedAdriana Mota, member-at-largeDaniel Wreesman, parent memberLuella Wright, member-at-large